Our Process

Five stages. Thirteen phases. One plan you can see.

Every villa we build follows the same disciplined sequence. Each phase has a clear scope, a responsible team, planned dates and a visible finish line, so you always know where your project stands and what comes next.

Phase 01

Design & Approvals

We study your plot, requirements and budget, and develop a design you can approve with confidence.

Sub-tasks
  • Site visit and plot study
  • Client brief and requirement workshop
  • Concept design and massing options
  • 3D views of the preferred option
  • Detailed working drawings
  • Structural design by a qualified engineer
  • Electrical and plumbing layouts
  • Itemised BOQ and preliminary cost estimate
  • Project schedule
You receive

Concept presentation, 3D views, approved drawing set, itemised BOQ and cost estimate, project schedule

Your involvement

Share your brief, review design options, and approve the final design and cost estimate

Phase 02

Site Preparation

We survey and secure the site and confirm the ground conditions before any construction begins.

Sub-tasks
  • Land survey and boundary marking
  • Soil testing
  • Site clearing and levelling
  • Temporary water and power connections
  • Site office and material storage
  • Excavation for foundations
You receive

Survey and soil test reports, site set-up photos

Your involvement

Optional site visit for the ground-breaking ceremony

Phase 03

Foundation

We build the footings and plinth that carry the whole house, with waterproofing to protect it for decades.

Sub-tasks
  • Setting out on site
  • Plain cement concrete bed
  • Footing reinforcement and concreting
  • Column starters
  • Plinth beam
  • Anti-termite treatment
  • Foundation waterproofing
  • Backfilling and compaction
You receive

Photographic record of reinforcement before each concrete pour; quality inspection reports

Your involvement

None required — progress is visible on My Canvas

Phase 04

Structure (Civil)

We build the reinforced concrete frame and the walls, floor by floor.

Sub-tasks
  • Columns
  • Beams and floor slabs (floor by floor)
  • Staircase structure
  • Blockwork or brickwork walls
  • Lintels and sunshades
  • Openings for doors and windows
  • Laboratory strength testing of concrete cubes from each slab
  • Curing and structural quality checks
You receive

Slab-by-slab photo record, engineer's inspection sign-offs, cube test reports

Your involvement

A structural walkthrough is recommended once the walls are complete

Phase 05

Roofing & Waterproofing

We complete the roof and seal the house against rain and heat.

Sub-tasks
  • Roof slab
  • Parapet walls
  • Terrace waterproofing
  • Slope finishing for drainage
  • Rainwater outlets
You receive

Waterproofing warranty

Your involvement

None required

Phase 06

Electrical (rough-in)

Concealed wiring is laid in the walls and slabs before plastering, following the approved electrical layout.

Sub-tasks
  • Concealed wiring laid in the walls and slabs
  • Switch and socket boxes
  • Main and sub distribution board positions
  • Wiring for lights, power, AC and data
  • Earthing
  • Provisions for solar, EV charging and CCTV (if selected)
You receive

As-built electrical layout

Your involvement

Confirm switch, socket and light positions during a site walkthrough

Phase 07

Plumbing (rough-in)

Water supply and drainage lines are laid before walls and floors are finished.

Sub-tasks
  • Concealed water supply lines
  • Hot water lines
  • Drainage and soil lines
  • Rainwater harvesting connections
  • Underground and overhead tank connections
  • Pressure testing of all lines
You receive

Pressure-test record, as-built plumbing layout

Your involvement

Confirm bathroom and kitchen fixture positions

Phase 08

Plastering & Flooring

Walls get their smooth finish and floors are laid in your chosen materials.

Sub-tasks
  • Internal plastering
  • External plastering
  • Floor levelling
  • Floor tiles, stone or wood
  • Bathroom wall tiling
  • Kitchen dado
  • Staircase cladding
  • Skirting
You receive

Material samples and approvals record

Your involvement

Select and approve flooring, tiles and stone

Phase 09

Fabrication

Metal and glass elements are made to measure and installed.

Sub-tasks
  • Window frames and glazing
  • Safety grilles
  • Staircase and balcony railings
  • Main gate and compound gate
  • Pergolas and canopies
  • Anti-rust treatment
You receive

Shop drawings for approval before fabrication

Your involvement

Approve designs and finishes

Phase 10

Painting & Finishing

Surfaces are prepared and painted, and woodwork is polished.

Sub-tasks
  • Wall putty and primer
  • Interior paint
  • Exterior weatherproof paint
  • Texture or feature walls
  • Wood polish
  • Metal paint for grilles and railings
You receive

Colour schedule, paint brand and shade record for future touch-ups

Your involvement

Approve colour scheme and sample patches

Phase 11

Electrical & Plumbing (fittings)

The visible fittings are installed and every system is tested.

Sub-tasks
  • Switches and sockets
  • Light fixtures and fans
  • Distribution boards
  • Sanitaryware and CP (chrome-plated) fittings
  • Water heaters
  • Pumps and tank controls
  • Full electrical and plumbing testing
You receive

Test reports, product warranties and manuals

Your involvement

Select fittings from the agreed range

Phase 12

Interiors & Landscaping

Interiors and outdoor spaces are completed to the approved design.

Sub-tasks
  • Modular kitchen
  • Wardrobes and storage
  • False ceilings and lighting
  • Doors and hardware
  • Loose furniture (if in scope)
  • Garden and planting
  • Hardscape, paving and driveway
  • Outdoor lighting
You receive

Interior drawings and 3D views, approved material board

Your involvement

Approve interior design and material selections

Phase 13

Final Inspection & Handover

We inspect every element in detail, rectify any snags, and hand over a complete, fully documented home.

Sub-tasks
  • Deep cleaning
  • Snag list inspection with you
  • Snag rectification
  • Final testing of all systems
  • Key handover
You receive

Keys and as-built drawings

Your involvement

Joint walkthrough and sign-off

—
After handover

A 12-month defect liability period.

Any issue during this period is logged, assigned and tracked to closure through My Canvas, just like the build itself.

?
Questions

Frequently asked.

How long does a villa take to build?

Timelines depend on the size, design and specification of the home. We provide a phase-by-phase schedule during Design & Approvals, which you can then track live on My Canvas.

How do payments work?

Payments are linked to completed phases, as set out in your payment schedule. You can pay each milestone securely online through My Canvas.

Can I change the design once construction starts?

Yes. You raise a change request on My Canvas, we show you the cost and time impact, and nothing changes until you approve it.

Do you take on projects other than villas?

Yes. We work only on homes, and that includes interiors for apartments and villas across Bengaluru: kitchens, wardrobes, ceilings, lighting and finishes, designed and delivered by the same team.

Can I visit the site?

Yes. We recommend scheduled walkthroughs at key milestones, coordinated with our site team for safety, and you can view the site at any time through the live camera feed.

What happens after handover?

You receive a complete handover file, and any defects during the defect liability period are logged and resolved through My Canvas.